Skip to main content

Removal and Preparation Scope Indefatigable Field Structures

Based on the Piece Small feasibility study completed in 2007, Shell UK Ltd awarded AF Offshore Decom the Piece Small removal and Preparation Scope.

Project status

      Sep 2008
      Dec 2010

      Main contractor for Planning, Engineering and Offshore Lift Preparations and partly Piece Small removal of six platform topsides from the Indefatigable Field. The contract format for this project was Lump Sum.

      • 13,300

        mT

      AF Gruppen

      Piece Small method

      The three topsides was removed by utilising the Piece Small method, which means the decommissioning was completed by cutting the platform into pieces, sorting and loading into containers before transporting to shore by supply vessels. 

      Utilising the piece small removal method, 3300mT were removed offshore and transported in containers to Great Yarmouth on the east coast of England for sorting, and recycling and disposal.

      Moreover, all preparations for the Reverse Installation Scope on three more platforms were completed. The work was finalised in August 2010.

      Scope Of Work

      • Project Management
      • Engineering
      • Haz. Waste mapping
      • Make safe
      • Preparation for lift
      • Piece small removal
      • Onshore Disposal

      Project info

      Project type: Fjerning og gjenvinning offshore
      Customer: Shell UK Ltd
      Contract type: Main Contractor for Planning, Engineering and Offshore lift Preparations. Lump Sum
      Entrepreneur: