Demolishing parts of the Ulven Transformer Station.

Demolition of building structures inside Ulven Transformer Station.

Project status

      Nov 2024
      May 2026
      • 6 MNOK ekskl. mva.

        Contract sum
      • Marthinsen & Duvholt AS

        Customer
      AF Gruppen

      Ulvenveien 109, 0665 Oslo

      Operational during demolition

      The project involves the planning and demolition of building structures inside Ulven Transformer Station. The facility remains operational throughout the entire demolition process, which requires great caution regarding the live electrical components. During the demolition process, temporary sealing is carried out at the demolition cuts against the remaining building structures.

      • Aerial photo of the building structures at Ulven Transformer Station in Oslo. The parts of the buildings that are to be demolished are marked in yellow.
        DEMOLITION CUT: The transformer station will stay operational during the demolition. Since some cuts are near buildings that must remain intact, carefulness in the demolition work is crucial.

      The demolition will be carried out in two phases. The first phase will begin in November 2024, while the second phase is planned for spring 2026.

      Project info

      Project type: Riving
      Business unit: AF Decom AS
      Customer: Marthinsen & Duvholt AS
      Contract type: NS8415