Energy performance contract (EPC) with Modum municipality
Modum municipality reduces annual energy consumption by 2,8 GWh through an energy performance contract with AF Energi
Project status
Jan 2019
Jun 2020
28 MNOK eksl. VAT.
Contract sum2,8 GWh
Annual reduction
Modum
Invests in energy efficiency
Over 18 months, AF Energi will implement approximately 140 energy-efficient measures across 21 buildings in Modum municipality. These measures include establishing a heating plant with a heat pump, installing an automatic energy monitoring system (AEOS), and replacing lighting with LED.
Besides conserving energy, these updates will provide a technical upgrade to the lighting systems, reducing maintenance requirements after installation.
Project info
Project type: Rehabilitering og energieffektivisering
Customer: Modum municipality
Contract type: Design and build contract
Entrepreneur:
Rikke Bjørnland
Project director
AF Energi AS