The Sandsli 360 project is divided into 3 construction phases, with the first encompassing 67 apartments which are already on sale and with building work scheduled to begin in May.

Sandsli 360 is split across a total of six buildings in a sunny area with beautiful natural surroundings on the elevation above the Håvardstunvatnet lake in the Fana district. The project is located close to a light rail stop in between the Lagunen Storsenter shopping mall and Bergen Airport. Nearby there are grocery stores, several major employers, hiking trails and fitness centres.

The contract is a turnkey contract with a total value of approx. NOK 404 million, excl. VAT.

Construction work will commence in Q2 2021 and is scheduled for completion in Q2 2024.