Contract K302 Heating and cooling system comprises the delivery and installation of equipment for cooling production, heat recycling and thermal energy storage with the associated distribution network. The gross building area is 63,000 m2 plus technical mezzanines. The heating and cooling system is planned to be partially prefabricated in modules and installed in place in order to ensure high quality during production and delivery.
The contract is a principal contract and is estimated at NOK 109 million excluding VAT.
Work starts in September 2017 and completion is expected for May 2020.
"We are very pleased that Statsbygg has proposed AF Gruppen as contractor for the heating and cooling system at Campus Ås. This is the largest energy contract AF Gruppen has ever won, and proves that our innovative solutions are space- and cost-effective», says CEO Morten Grongstad.