AF Gruppen shall excavate two rock cavern for deposit of waste material for Boliden Odda AS. In total AF Gruppen shall excavate 600.000 m3 of rock. The contract also includes other civil works. 

The construction start will be in January 2017 with completion in the summer of 2019.
The contract will have a value of approx. NOK 140 million excl. VAT. 

– AF appreciate to be chosen as contractor by Boliden Odda. We are looking forward to use our broad experience in tunneling and rock cavern construction in a challenging project, says Morten Grongstad, CEO of AF Gruppen.

For further information: 
CEO: Morten Grongstad, tel. +47  99 15 39 05
EVP Civil engineering: Arild Moe, tel. +47 91 37 62 65