Huldra A Disposal
In the beginning of 2016, Statoil awarded HMC the contract for EPRD of the Huldra facilities. AF was then awarded the disposal scope from HMC for the approximately 5000mT topside and the 5000mT steel-jacket.
Project status
Jan 2017
Aug 2019
The Huldra platform was regularly maintained until 2016 when it was decided to perform permanent well plugging. The offshore removal was performed in 2019 and offloaded at AF Environmental Base Vats near Haugesund where all structures were safely dismantled and disposed of.
Project info
Project type: Fjerning og gjenvinning offshore
Business unit: AF Offshore Decom AS
Customer: HMC